Sunday, February 7, 2010

The Foundation

Our first plan was to go for a Framed structure, with all the load supported by about 16 pillars, but once the estimate came, the same had to be pushed down though it was a nice design to save a few hundreds of thousands of what we really didn't have with us - money.

Now the earthworks for the load-bearing structure is almost over, the foundation is about 1m deep in most of the parts. Next we have to make a 10 cm sand filling all along the foundation.

Items purchased till now:
[All loads are in Mazda Tipper unless specified otherwise]

Crusher sand - 2.5 loads
Metal - 2 loads 1.5 inches & .5 load .75 inches.

No comments:

Post a Comment