Tuesday, November 16, 2010

Roof Slab Concrete

The structure of the home is thus complete, with the roof slab done on 3rd Nov 2010. It took 119 bags of cement. The workers and the contractor were blaming me saying it's too much steel they can't keep their feet on the platform. Whatever, Krishnakumar sir, the structural engineer, wouldn't do any compromise on it. Neither would I. Even while the concretion was going on, we bought a full length 16mm steel bar and added to it. The roof slab haas two pergolas

Friday, October 8, 2010

Plastering going on.. . Roof slab not yet done

Roof slab concrete is not yet done, due to some strike in the quarries which makes crusher metal and sand unavailable. Besides, the contractor doesn't have the materials for making the concrete slab platform. So its a near halt stage. But anyway plastering is going on in the ground floor at a slow pace. Now the two kitchens are done, the verandah is done, the prayer room is done and the dining room wall is also over.

Wednesday, September 8, 2010

Ground floor Structure complete

The ground floor main slab concrete was done as planned, thanks to Jesus there was no rain on the day, and it was good weather. Everything went fine, and the slab was completed by 3 O'clock. It took about 85 bags of cement [L&T Ultratech]. The staircase to the first floor was also done along with the slab. Now we have to wait a few weeks for the concrete curing, before the works for the 1st floor begins.

Sunday, July 4, 2010

Slab Concrete planned for this week

It's after a big interval, I'm posting in this. Our house-construction work has reached up to the ground floor main slab concrete planned for next week. Today I tried to free some place for unloading the crusher sand and metal in the plot, doing which I got bitten by a spider, and had to stop today's work. Besides, I'd to come to office.

The joinery - ground floor

All the joinery for the ground floor was made by Mr. Salim's carpenters [ Lulu furniture, Karukadam, Kothamangalam]. They were made of used[old] wood. Doesn't look as good as new ones, they say. But I feel it's enough. Many people say good opinion about it, though some are against it. This was the thing that delayed the work most. The joinery pieces were delivered more than a month later than when it was supposed to be delivered. Since I was insistent on the lintel to be made only after fixing the joinery, we had to pend the works for a few weeks. In between, the septic tank was constructed, though.

The walls

Laterate bricks[ vettukallu] was used for all the 20 cm walls. For 10 cm walls [interior- seperation between kitchen and work area, toilet and store room] we used cement bricks. For septic tank also 6 in cement bricks were used.Just above the joinery height, there's the lintel concrete, which varies in thickness with the nature of the joinery under, and the span etc, all according to Krishnakumar sir's drawing[ Associated Structural consultants, Kochi]. In some places it's 30 cm thick. In others, mostly 15cm. Over the lintel, 3-4 layers of bricks[20cm laterate bricks] were used, to reach the main slab level.

Foundation belt concrete

A belt concrete was done over the foundation rubble work, with 15 cm thickness and 30 cm[or 40 cm i don't remember exactly]. Some 30 bags of cement and about 1 tonne steel was purchased[exact amount of steel I don't remember. Will update later].