Wednesday, September 8, 2010

Ground floor Structure complete

The ground floor main slab concrete was done as planned, thanks to Jesus there was no rain on the day, and it was good weather. Everything went fine, and the slab was completed by 3 O'clock. It took about 85 bags of cement [L&T Ultratech]. The staircase to the first floor was also done along with the slab. Now we have to wait a few weeks for the concrete curing, before the works for the 1st floor begins.